Code | One | Description | Amount | Price (€) | Amount (€) | Impact of labor (€) | Labor (h) | Impact of labor (%) |
RE0005 | m² | Plaster crushing to bouna view to the vertical wall | 1,00 | 7,19 | 7,19 | 5,45 | 0,33 | 75,80 |
| | B1 Construction Gypsum Trim a B1 in Buena Vista, on the vertical wall, up to 3 m high, instead of the previous placement of Anti -Calis mesh material, with lifeguards. | | | | | | |
%01a | % | Auxiliary costs on the labor | 0,02 | | 0,11 | | | |
%02 | % | Indirect costs | 0,03 | | 0,21 | | | |
| % | Estimation of the degree of difficulty or uncertainty (normal: 1.00) | 1,00 | | | | | |
REU0009 | m³ | B1 construction plaster, according to UNE-EN 13279-1, D22, with P.P. Fiberglass, 5x5 mm light, flexible and imputable with time passing, 70 g/m² surface mass and 0.40 mm thick thick, to mount plastic and metal lifeguards, stable for a the action of sulfates. | 0,02 | 78,85 | 1,42 | | | |
MOU0001 | h | 1st plasterist officer. Professional level VIII (Source: IVE). / More information | 0,21 | 17,93 | 3,77 | 3,77 | 0,21 | |
MOU0002 | h | Ordinary plasterist pawn. Professional level XII (Source: IVE). / More information | 0,12 | 14,00 | 1,68 | 1,68 | 0,12 | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Written by Vicente Almudéver | | | | | | |
| | | | | | | | |
| | Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Update 31/05/2013 | | | | | | |
| | Zone València | | | | | | |
| | Remarks: | | | | | | |
| | .......... | | | | | | |
| | Validated by Francesc Company Gandia | | | | | | |
| | | | | | | | |
| | Validated by date 15/10/2018 | | | | | | |
| | Remarks: Preu CYPE 9,13 €. Preu € 6,70 €. Preu ITEC 9.77 (sense comprovar) €. | | | | | | |
| | edit price | | | | | | |
|