RE0010m

Reinforcing wrought IPE-140 up to 4 m. Includes preliminary work and shoring.

1,00105,16105,1656,303,8653,54
Functional replacement of slabs, each consisting of reinforcing beam profiles using IPE-140 S-275-JR, including the following materials and works: 1.1 Sanitation coatings lower the beams and brushed surface. 1.2 Perforated coatings in areas of support profiles. 1.3 Shoring of the section of beam or joist. 1.4.- Placing plates on the beams and walls, using anchors. 1.5.- work placement in the metal profiles, one piece each beam, upon application of a double layer of paint antioxidant, welded plate. In any case, the solution will be adjusted to the standard CTE / SE A. 1.6.- flush profile so that the minimum and maximum separation between the upper wing profile and the underside of the beam be 5mm and 20mm, respectively. 1.7.- Fastening profile plates to anchor the beams. 1.8.- Contact and entry load beam.
%01a%Ancillary costs of labor0,020,80
%02%indirect costs0,031,80
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0133uPlacing anchor plate steel S-275-JR, 250x250x10 mm.0,6642,6328,144,880,42
RE0141mPerforated gypsum underside of the beam1,003,683,683,500,37
REU0031kgMortar structural resins, Aplicatec R4 product in bags of 25 kg.6,100,653,97
REU0173kgRolled steel UNE-EN 10025 S-275-JR simple piece of hot rolled series IPN, IPE, HEB, HEA, HEM and UPN, worked in the workshop, applied structural reinforcements.13,880,7910,97
REU0067hEquipment and auxiliary elements for electric welding.0,033,090,090,090,03
REU0158uAir Liquide electrode Spezial 3,25mm x 450.8,000,191,52
MOU0022hOfficial 1st welder. Professional level X (Source: IVE). / More information0,1517,932,692,690,15
REU0030kgPainting house TKROM can 25kg, primer antocorrosiva S / R Gray 411 or similar.1,502,093,14
REU0161kgSolvent universal primer TKROM antixidante can 5 kg.0,011,770,03
RE0143mHealthy structural concrete beam underside.0,4518,288,235,770,42
RE0144Shoring concrete beam forged.0,505,332,671,940,12
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information1,0517,9318,8318,831,05
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information1,3014,3118,6018,601,30
written by Vicente Almudéver
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 4/03/2013
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 2018-10-16
observations: Partides similars: Preu Cype (reforç de biga o bigueta de formigó armat, mitjançant perfil d'acer S275JR, laminat en calent, sèrie IPE 140, amb capa d'imprimació anticorrosiva, disposat a la cara inferior de la biga, fixat amb adhesiu tixotròpic de dos components a base de resina epoxi) EHP040 32,48 €. Preu IVE (reforç de bigueta de formigó armat amb biga IPE 140) REHR.9bda 25,53 €. Sense treballs previs. Preu ITeC (reforç inferior de forjat amb bigues transversals de perfil d'acer per a estructures) 44SL2237 284,20 € / u. sense revisar
Edit price