REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionAmountPrice (€)Amount (€)Impact of labor (€)Labor (h)Impact of labor (%)
RE0023

Chopped tile grip material

1,004,704,704,480,3095,32
Demolition of the cement mortar as a grip material from the tiles to the roof, with manual means, even the removal of waste and the load on the truck or in the container, without including the transport to the landfill.
%01a%Auxiliary costs on the labor0,020,09
%02%Indirect costs0,030,13
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information0,1514,312,152,150,15
MOU0023hSpecialist pawn under construction. Professional level XI (Source: IVE). / More information0,1515,502,332,330,15
Written by Vicente Almudéver
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 4/03/2013
Zone València
Remarks:
..........
Validated by Francesc Company Gandia
Validated by date 19/10/2018
Remarks: CYPE Preu DQF010 4,89 €. Preu Ive DDDQ36A 4,09 €.