RE0036

Demolition of empty container

1,006,766,766,440,4595,27
Demolition of brick wall with debris removal and loading truck or container, excluding transport to the landfill, according NTE / ADD-9.
%01a%Ancillary costs of labor0,020,13
%02%indirect costs0,030,19
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,4514,316,446,440,45
written by Vicente Almudéver
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 3/03/2013
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 22/10/2018
observations: Preu Cype DPT020 5,46 €. Preu IVE DDDF2aba 4,77 €. Preu ITeC K2163511 5,81 € sense revisar.