REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0040

Demolition of factory coated interior partition, 4/5/7 cm thick.

1,005,265,265,010,3595,25
Demolition of factory coated interior partition, consisting of simple hollow brick from 4 to 7 cm thick, with manual means, without affecting the stability of the adjacent building elements. Even demolition proportion of its coatings (plaster, mortar, tiles, etc.), carpentry and recessed installations, following the dismantling of the leaves; cleaning, gathering, removal and manual loading debris truck or container.
%01a%Ancillary costs of labor0,020,10
%02%indirect costs0,030,15
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,3514,315,015,010,35
written by Vicente Almudéver
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 9/07/2013
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 23/10/2018
observations: Preu Cype DPT020 4,75 €. Preu IVE DDDF2aba 4,77 €. Preu ITeC K2163511 5,81 € sense revisar
Edit price