REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionQuantityPrice (€)Amount (€)Jobmane repercussion (€)Workforce (H)Job Maging Repercussion (%)
RE0041

Demolition of the interior partition of the covered factory, perforated brick thickness of 11 cm.

1,009,329,328,870,6295,17
Demolition of the internal partition of the covered factory, formed by perforated brick of 11/12 cm thick, with manual means, without affecting the stability of the construction elements contiguous. Even proportional part of the demolition of its coatings (plaster, mortar, delicat, etc.), embedded facilities and carpentry, previous eviction of leaves; Cleaning, collection, disposal and cargo manual of waste in truck or container.
%01a%Auxiliary costs on labor0,020,18
%02%Indirect costs0,030,27
%Estimation of degree of difficulty or uncertainty (normal: 1.00)1,00
MOU0006hOrdinary pawn under construction. Professional Level XII (Source: Ive). / More information0,6214,318,878,870,62
Drafted by Vicente Almudéver
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 9/07/2013
Zone València
Observations:
..........
Validated by Francesc Company Gandia
Validated with date 23/10/2018
Observations: Preu Cype Dpt020 € 9.20. Preu IVE DDDF2CCA 7,15 €. Preu ITeca (fins a 15 cm de gruix, amb martell manual) K2164671 € 9.24. Sense comprovar-ho.