CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0046

Demolition concrete slab, thickness 10/12 cm.

1,0017,2617,2616,441,5795,25
Demolition of continuous mass concrete pavement 10 cm thick, with jackhammer compressor, not including the demolition of the support base or damage the adjacent building elements. Even proportion of cleaning, gathering, removal and manual loading debris truck or container.
%01a%Ancillary costs of labor0,020,33
%02%indirect costs0,030,49
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0184hJackhammer devastating0,454,081,841,840,45
REU0185hCompressor diesel portable medium pressure 10 m / min.0,358,803,083,080,35
MOU0023hPawn specialist in construction. Professional XI (Source: IVE). / More information0,4215,506,516,510,42
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,3514,315,015,010,35
written by Vicente Almudéver
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 9/07/2013
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 23/10/2018
observations: Preu Cype DRS070 10,27 €. Preu IVE DDDE1a 109,87 € (en metres cúbics). Preu ITeC K2192311 11,49 € sense revisar.