REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0061u

Aids palette to wedge three major closures m².

1,00103,47103,4798,546,0095,24
Aids palette to wedge exterior carpentry greater than 3 m², including removal of excess material and final cleaning.
%01a%Ancillary costs of labor0,021,97
%02%indirect costs0,032,96
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information3,5017,9362,7662,763,50
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information2,5014,3135,7835,782,50
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 09/07/2013
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 27/11/2018
observations: