REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionAmountPrice (€)Amount (€)Impact of labor (€)Labor (h)Impact of labor (%)
RE0065m

Canaleta's disposition collected water

1,00130,77130,7714,190,8810,85
Supply and placement of prefabricated gutters for water collection, polymer concrete, section 20x20/15 and galvanized zipper, unit connected to the sewerage network with PVC pipe, prepared from the ditch after opening with electricity , Canaleta Falcado, concrete and built pieces -in an existing solera, perimeter auction with cement and finish tiles, removal of excess material and cleaning
%01a%Auxiliary costs on the labor0,020,28
%02%Indirect costs0,033,80
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0241uConstruction material for simple intervention masonry1,2045,0054,00
REU0242mGutter 20zx15 Interior, polymer concrete with galvanized metal network.1,0041,0041,00
REU0243mFlimonry material for drainage of kittens embedded in concrete solera.0,5035,0017,50
MOU0005h1st officer under construction. Professional level VIII (Source: IVE). / More information0,4417,937,897,890,44
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information0,4414,316,306,300,44
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 09/07/2013
Zone València
Remarks:
..........
Validated by Francesc Company Gandia
Validated by date 29/11/2018
Remarks: Preu CYPE (dimensions 150x143 mm, sense excavació ni acabat perimetral) com a 66,96 €. IVE Preu (dimensions 200x265 mm, sense excavació ni acabat perimetral) EISA18CDCA 95,52 €. Preu ITEC (dimensions 200x240 mm, sense excavació ni acabat perimetral) ED5H2AB5 135,14 €
edit price