RE0071

Demolition of plaster ceiling fixed

1,008,468,468,060,5095,27
Demolition of ceiling plaster cladding fixed to <2.50 m tall, with removal and loading container, no transport to landfill.
%01a%Ancillary costs of labor0,020,16
%02%indirect costs0,030,24
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,2517,934,484,480,25
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,2514,313,583,580,25
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 05/11/2014
zone València
observations:
..........
Validated by Francesc Company Gandia
Validated date 12/12/2018
observations: Preu Cype DRT020 7,67 €. Preu IVE DDDR4b 3,38 €. Preu ITeC K218A210 5,31 €