CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0130m

Training stepped ceramic staircase.

1,0019,7219,729,530,5748,33
Training scaled-scale hollow ceramic brick received with cement mortar M-5, sobrela slab or scale back as basis for the subsequent laying of finishing steps. Includes: Redesigning the layout and stepped on the walls. String extended between the first and the last step. Cleaning and wetting the slab. Training steps. Project measurement criteria: length of the axis of the route of the scale, measured enprojecció horizontal.
%01a%Ancillary costs of labor0,020,19
%02%indirect costs0,030,57
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0190uDouble hollow ceramic brick, to cover, 33x16x7 cm, according to UNE-EN 771-1.31,000,206,20
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,03115,503,23
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,3817,936,816,810,38
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,1914,312,722,720,19
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 13/06/2013
zone València
observations:
..........
Validated by Josep Mestre Ruiz
Validated date 7/06/2017
observations: Preu Cype HYP010 17,96 €. Preu IVE EFFW4a 10,37 €