CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0201u

Replacing sewer overflow balcony.

1,0020,5420,548,060,5039,24
Replacement of sewer overflow balcony including extending hole in the wall of the factory, before withdrawing pipe, installation of new sewer executed PVC profile rectangular 5x4 cm, and even during filling perimeter, vol least 3 cm.
%01a%Ancillary costs of labor0,020,16
%02%indirect costs0,030,59
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0657uCartridge neutral silicone putty.0,153,200,48
REU0656uGargoyle anodized aluminum 50x50 mm section, made from square profile aluminum and finished with 45 ° cutting angle forming.1,002,252,25
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,2517,934,484,480,25
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,2514,313,583,580,25
REU0241uBuilding material for simple operation albañileria0,2045,009,00
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 22/01/2015
zone València
observations: AO0009
..........
Validated by Josep Mestre Ruiz
Validated date 9/06/2017
observations:
Edit price