RE0201u

Replacement of the outer balcony slope.

1,0020,5420,548,060,5039,24
Replacement of spillman balcony pipes including the expansion of the hole in the factory wall, the removal of previous pipes, the new installation of pipes executed with a rectangular PVC profile of 5x4 cm, even slope and filled with perimeter. , minimum flight of 3 cm.
%01a%Auxiliary costs on the labor0,020,16
%02%Indirect costs0,030,59
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0657uNeutral silicone massilla cartridge.0,153,200,48
REU0656uAnodized aluminum gargoia, 50x50 mm section, made with square aluminum profile and a 45 ° cut -shaped finish.1,002,252,25
MOU0005h1st officer under construction. Professional level VIII (Source: IVE). / More information0,2517,934,484,480,25
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information0,2514,313,583,580,25
REU0241uConstruction material for simple intervention masonry0,2045,009,00
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 22/01/2015
Zone València
Remarks: AO0009
..........
Validated by Josep Mestre Ruiz
Validated by date 9/06/2017
Remarks:
edit price