REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0203

Treatment of surface finish in interior marble pavement.

1,0013,1013,1012,221,1693,28
Polishing and polishing natural stone flooring and polished by using polishing machine polishing machine with plate steel wool or synthetic sponge, interior marble pavement; polishing consist of three phases: the first (Edged or recess) to remove cells that might exist using a mass of 60, according to the type of natural stone and the state where it is the pavement; the second (planned or grinding coarse) to remove scratched and defects produced in the previous phase, with abrasive grain 120, extending then again paste to together, keeping the surface wet 24 hours, leaving hardened other 48 hours before following process; and third (tuned) with abrasive grain 220; polishing is performed by using the method of crystallizing masses of 400 or higher with subsequent application of polish product, once it is perfectly dry and uniform pavement. Even after the proportion of union coarse sanding, removal of sludge from the fine polishing and cleaning prior to polishing.
%01a%Ancillary costs of labor0,020,24
%02%indirect costs0,030,37
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0422hPolisher for paving stone or terrazzo, consisting of turntables that are coupled to a series of grinding, chilled water.0,354,451,561,560,35
REU0423hPolishes for crystallizing and polishing of stone or terrazzo floors, made of plate steel wool or synthetic sponge.0,222,350,520,520,22
REU0426kgGrouting mortar for coatings, interior or exterior, natural stone, polished or polish, made of cement, aggregates force of marble dust, pigments and special additives resistant to alkalis.0,151,800,27
MOU0052hOfficial 1st polisher pavements. Professional level VIII (Source: IVE). / More information0,4117,937,357,350,41
MOU0053hAssistant polisher pavements. Professional level X (Source: IVE). / More information0,1815,502,792,790,18
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 20/03/2014
zone València
observations:
..........
Validated by Josep Mestre Ruiz
Validated date 9/06/2017
observations: Preu Cype RSP030 8,26 €. Preu IVE (rebaixat) RRSP4a 4,52 €, (polit) RRSP5a 3,37 €, (abrillantat) RRSP6a 2,81 €. Preu ITeC E9Z2A100 7,52 €.