RE0207m

Coating step natural stone Crema Levante.

1,0072,1572,1527,691,7438,38
Supply and installation of siding with straight step on scale of 100 cm wide, by assembling the following elements: Crema Levante extended marble, polished finish and cream marble front Levante 3 and polished finish 2 cm thick respectively, face and polished edges, received all with cement mortar M-5, placed on a stepped before (not included in the price). Even grouting cement mortar joints, CG1 for meeting minimum (between 1.5 and 3 mm), with the same tone of the pieces.
%01a%Ancillary costs of labor0,020,55
%02%indirect costs0,032,09
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0416mLying to step straight national Marble Cream Lift length up to 100 cm and 3 cm thick, expensive and polished edges.1,0024,7524,75
REU0417mStep forward for national marble, Crema Levante, up to 100 cm long by 16 cm wide and 2 cm thick, polished.1,0012,7512,75
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,04115,504,04
REU0112kgGrouting mortar for coatings, interior or exterior, natural stone, polished or polish, made of cement, aggregates force of marble dust, pigments and special additives resistant to alkalis.0,151,880,28
MOU0033hOfficial 1st tiler. Professional level VIII (Source: IVE). / More information0,5817,9310,4010,400,58
MOU0034hAssistant tiler. Professional level X (Source: IVE). / More information0,5815,508,998,990,58
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,5814,318,308,300,58
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 20/03/2014
zone València
observations:
..........
Validated by Josep Mestre Ruiz
Validated date 9/06/2017
observations: Preu Cype REP020 50,31 €. Preu IVE (crema marfil) ERSPKaaaac 41,46 €.