RE0210

Evened plastered with cement mortar.

1,0036,0336,0314,980,9041,58
Lining interior walls and exterior with plaster evened mortar industry for plastering, 15 mm thick, gray, smooth finish for the completion of the base layer coated continuous double-layer finish swirls, thickness 15 mm, applied manually, reinforced and reinforced with mesh antiàlcalis changes in material and forged fronts.
%01a%Ancillary costs of labor0,020,30
%02%indirect costs0,031,04
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0402kgIndustrial mortar for plastering, 15 mm thick, gray, smooth finish, composed of high strength cement, selected aggregates and other additives, type GP CSIV W0, according to UNE-EN 998-1.28,200,6819,18
REU0403Fiberglass mesh, 10x10 mm light antiàlcalis, 200 to 250 g / m² surface mass 750 to 900 microns thick, with 25 kp / cm² of tensile strength, to assemble monolayer mortars.0,222,420,53
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,5817,9310,4010,400,58
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,3214,314,584,580,32
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 24/03/2014
zone València
observations:
..........
Validated by Josep Mestre Ruiz
Validated date 9/06/2017
observations: Preu Cype RBB020 17,89 €. Preu IVE ERPE1ccab 14,60 €. Preu ACAE UPRXCOT053 13,68 €.