RE0224

Solera T1 mass concrete, 10 cm thick, finished bearing.

1,0033,3933,3920,231,2260,59
Training continuous mass concrete pavement 10 cm thick, made of concrete HM-20 / M / 12 / I made in central and poured bomb; treated superficially mortar rolling, light gray, made of cement, selected aggregates quartz, organic pigments and additives with a yield approximately 3 kg / m², sprinkled manually on the concrete still fresh and subsequent application of liquid curing colorless , yield 0.15 kg / m². Even w / w surface cleaning medium, extended and vibrated concrete the rule by vibrant embroquetat or connection of external elements (walls of boxes, Boner, sifòniques boxes, etc.) networks installation facilities executed under the pavement, mechanical swirling across the surface to get the mortar to be fully integrated into the concrete and final cleaning of the finished surface. Including the preparation of the base layer existing job boards and concrete, using mechanical retraction cut diamond blade in less 2/3 of the thickness of the slab, expansion joints and perimeter together.
%01a%Ancillary costs of labor0,020,40
%02%indirect costs0,030,96
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0480Concrete HM-20 / B / 20 / I, made central.0,1665,1010,42
REU0481kgMortar tread, color Natural Gray, made of cement, selected aggregates quartz, organic pigments and additives, with a density of 1330 kg / m³, a compressive strength of 75,000 kN / m² and abrasion resistance with Böhme method UNE-EN 13892-3 10.9 cm³ / 50 cm².3,000,461,38
REU0482hMachine front Dumper 2 download t. payload.0,029,450,180,180,02
REU0483hRule 3 m vibrant.0,024,670,070,070,02
REU0484hRemolinador mechanical concrete.0,5718,1510,3510,350,57
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,2517,934,484,480,25
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,3614,315,155,150,36
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 24/03/2014
zone València
observations: Notes de l'autor?
..........
Validated by Francesc Company Gandia
Validated date 1/07/2019
observations: Preu cype ANS010 13,38 €. Preu IVE EISC.8cab diam 120 24,94€