CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0227

Healthy indoor stone walls viewed

1,0030,1830,1817,401,3657,65
Healthy stone walls, cloth interior on housing, consisting of: Empty boards stone in a depth of 2 to 5 cm, stones and bricks replace degraded and cleaned with a metal brush. Fill joints, gaps and shacks support base with mortar plastering, directly or coatings. Also stacking, loading and removal of debris and generated truck or container
%01a%Ancillary costs of labor0,020,21
%02%indirect costs0,030,67
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0060Chopped exterior wall / interior cement mortar, thickness less than or equal to 3 cm1,006,996,996,660,68
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,2817,935,025,020,28
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,4014,315,725,720,40
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,03115,503,47
REU0241uBuilding material for simple operation albañileria0,1845,008,10
observations:
Muro adjusted Medianero considerando completely remove the lining of plaster or cement mortar existente, dejar hasta seen muro ordinary masonry.
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 31/10/2014
zone València
observations: AO0002-PK0147
..........