RE0241u

Essay Verification of evacuation network

1,00271,62271,6223,251,508,56
Tests of service of the evacuation networks of buildings. Hydraulic final tests of the wastewater and rainwater evacuation network, according to the document recognized by the Generalitat Valenciana DRC 08/09. In addition to hydraulic partial tests in non-buried sections of the evacuation network, per unit of inspection, according to the document recognized by the Generalitat Valenciana DRC 08/09.
%01a%Auxiliary costs on labor0,020,47
%02%Indirect costs0,037,90
%Estimation of degree of difficulty or uncertainty (normal: 1.00)1,00
REU0720uFinal service test to be carried out by laboratory accredited in the corresponding technical area, to verify the correct functioning of a group of private facilities along with the general installation of water supply from which they depend on, in conditions of simultaneity. Even displacement to work and results report.1,00240,00240,00
MOU0023hPawn specialist in construction. Professional level XI (Source: Ive). / More information1,5015,5023,2523,251,50
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 31/10/2014
Zone València
Observations: A00002-PK0101
..........
Validated by Francesc Company Gandia
Validated with date 11/07/2019
Observations: Preu Cype XRI130 211,42 €. Preu IVE CSSV.2a 224,32 €.