REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionAmountPrice (€)Amount (€)Impact of labor (€)Labor (h)Impact of labor (%)
RE0261m

Assembly and dismantling and hanging, in the inner courtyard

1,00174,40174,40
Mounted and disassembled of scaffolding hanging on a facade for 25 ml high, even installation with upper counterbalance, maintenance, lower protection tray, safety and transport systems.
%01a%Auxiliary costs on the labor0,02
%02%Indirect costs0,033,48
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0091uTransportation to work and removal of the suspended motorized traction platform, 2 m long, consisting of one or more modules 90 cm wide, to work on vertical walls up to 30 m high, composed of role , railings, elevator elevators, cables and suspension structure, old system, fishing for suspension and other safety devices.0,10210,0021,00
REU0089uMotorized unit of disassembly of suspended platforms, 2 m long, consisting of one or more modules 90 cm wide, to work on vertical walls up to 30 m high, composed of role, railings, elevator equipment, Cables and suspension structure, anticiac system, suspension fishing and other safety devices.0,10279,0027,90
RE0107uAssembly and dismantling of pedestrian crossing. Section 15 ml.0,10550,1755,02
REU0088uAssembly of motorized traction platforms in suspension, 2 m long, consisting of one or more 90 cm width modules, to work on vertical walls up to 30 m high, composed of role, railings, equipment of equipment The elevator, cables and suspension structure, anticiac system, suspension fishing and other safety devices.0,20335,0067,00
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 22/01/2015
Zone València
Remarks: AO0009
..........
Validated by ?
Profile ?
Validated by date 00/00/0000
Remarks: Notes del validador?
edit price