REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0303

Structural reinforcement forged pipe system Herms CR DIT 289 / R, 100x100x4.

1,00197,15197,1568,744,7234,87
Reinforcing wrought comprised: - Shoring of the affected area to repair, if necessary. - Demolition of walls affected a height not exceeding 35-40 cm. (Removal of debris, loading and transport to landfill) even replenishing it once held reinforcement. - Chopped coating beams along the entire length, removal of debris, loading and transporting debris to landfill. - Diverting electricity or plumbing installations affected. - Lifting materials. - Priming the underside of the beam of concrete with epoxy resin Sikadur 32 FIX. - Installation of concrete beam in each of the first row of M8 70 mm long bath prior epoxy resins. - Placement with ancleje chemical metal plates posttensió house commercial HERMS S.A. - Installation of metal profile galvanized steel tubes and 100x100x4 90x90x4 with two rows of upper metal connectors - System HERMS D.I.T. 289 (together by screws socket with a minimum of 45 cm), with a top layer of mortar controlled retraction SIKA TOP 122 until after the spill the sides award posttensió screws - available two lines of barriers AEH-B500SD corrugated steel 10mm on each side of the joints between the sections of beam extentible - Delete shoring. - Protection of metallic elements (profiles and plates) by projection of rock wool or similar with a minimum thickness of 3-4. Measurement criteria: Applies considering a percentage interest of 70 cm between the joists, and the impact is viguet 1.43 ml / m² forged.
%01a%Ancillary costs of labor0,02
%02%indirect costs0,03
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0302mStructural reinforcement forged pipe system Herms CR DIT 289 / R 100x100x4.1,43137,87197,1568,744,72
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 27/11/2013
zone València
observations: Notes de l'autor?
..........
Validated by ?
profile Notes del validador?
Validated date 00/00/0000
observations: Notes del validador?
Edit price