CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF MANPOWER (€)MANPOWER (H)IMPACT OF WORKFORCE (%)
RE0306m

Reinforcing beam of wood with metal xapons 8 mm thick

1,0067,8767,8723,941,7735,27
Strengthening wooden beam section varies depending on the floor, by means of lateral confinement for his greater dimension, with two metal xapons 8 mm thick, of hot rolled steel S275JR according to UNE-EN 10027, faced about the sides of the timber, and received four interns per screws, washers and nut screwed with torque wrench on drills practiced on healthy wood.
%01a%Ancillary costs on labor0,020,48
%02%indirect costs0,031,96
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0330hOfficial 1st metal0,3215,965,115,110,32
REU0331hmetal specialist0,4515,466,966,960,45
REU0198hAssistant estructurista encofrador and reinforced concrete.0,2014,702,942,940,20
REU0010hOfficial 1st construction.0,3515,675,485,480,35
REU0012hOrdinary laborer construction.0,2014,312,862,860,20
REU0385kgS275JR steel sheet26,001,4938,74
REU0164mAM12x1000 HILTI threaded rod, galvanized 4.8.0,851,921,63
REU0204hmechanical drill0,252,350,590,590,25
REU0163uFlat washer A13 / 24 galvanized.8,000,050,40
REU0162uM12 galvanized hex nut.8,000,090,72
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 31/10/2014
zone ?
observations: AO0002-PK0038
..........
Validated by ?
profile Notes del validador?
Validated date 00/00/0000
observations: Notes del validador?