RE0311

Health at the beginning of the concrete pillars. Mortar structural.

1,0064,5264,5229,191,8045,24
Pillars' boot repair, consisting of: chop of concrete, sanale and cleaning with sand and water until they perfectly discovered the armor, passed from them, placement of the complementary armor if necessary, Armor coating with low concrete tixotropy, with replacement of the concrete section and waste load.
%01a%Auxiliary costs on the labor0,020,58
%02%Indirect costs0,031,86
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0264uHilti / Kango Electric Hammer electric.0,2016,003,20
REU0145kgSIKA CORROSION INHIBITOR AMBATEC Top 110-Epocem and Union Bridge, 4kg Boat, 3 components: A+B+C.1,754,157,26
REU0031kgMortar of structural resins, R4 applied product, in bags of 25 kg.34,500,6522,43
MOU0005h1st officer under construction. Professional level VIII (Source: IVE). / More information0,9517,9317,0317,030,95
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information0,8514,3112,1612,160,85
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 27/11/2013
Zone València
Remarks: Notes de l'autor?
..........
Validated by ?
Profile Notes del validador?
Validated by date 00/00/0000
Remarks: Notes del validador?
edit price