REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0311

Healthy start on concrete pillars. Mortar structure.

1,0064,5264,5229,191,8045,24
Repair boot pillars, consisting of: crushed concrete coatings, sanitation and clean water and sandblasted until he discovered perfectly armor, passivation of the same, installation of additional armor if necessary, coating concrete reinforcement with low thixotropy with replacement of the concrete section and loading debris.
%01a%Ancillary costs of labor0,020,58
%02%indirect costs0,031,86
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0264uHilti electric demolition hammer / Kango.0,2016,003,20
REU0145kgSika Armatec top 110 Period-corrosion inhibitor and bonding can 4kg, three components: A + B + C.1,754,157,26
REU0031kgMortar structural resins, Aplicatec R4 product in bags of 25 kg.34,500,6522,43
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,9517,9317,0317,030,95
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,8514,3112,1612,160,85
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 27/11/2013
zone València
observations: Notes de l'autor?
..........
Validated by ?
profile Notes del validador?
Validated date 00/00/0000
observations: Notes del validador?
Edit price