CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0312

Demolition mortar base layer for flooring, 50 mm thick.

1,0010,8910,8910,370,7095,22
Demolition of existing base screed mortar inside the building, up to 5.6 cm thick, with manual means, without damaging the adjacent building elements, to the upper left view of the joists. Even w / w cleaning, gathering, removal and manual loading or container debris truck
%01a%Ancillary costs of labor0,020,21
%02%indirect costs0,030,31
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0023hPawn specialist in construction. Professional XI (Source: IVE). / More information0,3015,504,654,650,30
MOU0006hOrdinary laborer in construction. Professional level XII (Source: IVE). / More information0,4014,315,725,720,40
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 31/10/2014
zone València
observations: AO0002-PK0039
..........
Validated by ?
profile Notes del validador?
Validated date 00/00/0000