CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0363m

Sewn static coating with epoxy mortar on brick.

1,0042,0042,0032,502,8777,38
Sewn on static brick through B 500 S steel staples welded from 6 to 12 mm in diameter in the form of Z, placed in coves work carried out in the form of the claw anchor will be placed staple binding the two walls to sew once executed drilling or taste to stay and infused both the surface and the work itself or staples to fix Sika Sika period or any product that facilitates the adhesion of the old work the new volume and filling with special Sika repair mortars or Betlor or similar tapessin are cracks and gaps to prevent loss of grout with thixotropic paste, and finally placed a mesh type mallatex thick on the surface previously the plaster exterior.
%01%ancillary costs0,020,80
%02%indirect costs0,031,20
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0028hSpecialist sewn static palette. Professional level VII (Source: IVE). / More information0,9418,3617,2617,260,94
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,9614,3113,7413,740,96
REU0031kgMortar structural resins, Aplicatec R4 product in bags of 25 kg.2,700,651,76
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,01115,500,58
REU0015kgSteel profiles B-500 S-6 / 16mm rods corrugated cut supplies on site.0,900,780,70
REU0203hResin injection equipment0,681,220,830,830,68
REU0204hmechanical drill0,282,350,670,670,29
REU0206kgEpoxy resin for injections0,2216,203,56
REU0036m44 Armatex fiber mesh plaster.1,100,820,90
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 04/11/2014
zone València
observations: AV0045-PK0004
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?