REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0371u

Restoration of support from balcony area 1.50 m².

1,00219,63219,63139,0310,5063,30
Restoration of the balcony supported by all parties including chopped loose, poorly adhered or damaged, you must crush all that is not in good condition, with removal of debris and cargo. Removing all the existing oxide layer on the beam supporting the balcony with barbed metal cleaning brush or sandblasting pressure until it is completely clean. Application Period 110 pasivador oxidation Sika or similar application Sika Fixed Period or product to serve as bridges between the old and the new surface over the entire surface and regeneration of existing volume lost incorporating armor healthy through the beam of high-strength repair mortars Sika or similar type incorporating mallatex thick middle layer of the fronts of the trays. The regeneration of the volume executed identically to the existing size and shape.
%01%ancillary costs0,024,18
%02%indirect costs0,036,28
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0204hmechanical drill1,402,353,293,291,40
REU0145kgSika Armatec top 110 Period-corrosion inhibitor and bonding can 4kg, three components: A + B + C.0,754,153,11
REU0031kgMortar structural resins, Aplicatec R4 product in bags of 25 kg.48,000,6531,20
REU0016kgMortar Structural type bag 25kg, product aplicatec R3.7,000,855,95
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,10115,5011,55
REU0015kgSteel profiles B-500 S-6 / 16mm rods corrugated cut supplies on site.4,000,783,12
REU0203hResin injection equipment1,101,221,341,341,10
REU0206kgEpoxy resin for injections0,9016,2014,58
REU0036m44 Armatex fiber mesh plaster.0,800,820,66
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information5,5017,9398,6298,625,50
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information2,5014,3135,7835,782,50
-0,03
observations:
Trays are considered Mirador balconies with an area not exceeding 1.50 m².
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 04/11/2014
zone València
observations: AV0001
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?
Edit price