REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionAmountPrice (€)Amount (€)Impact of labor (€)Labor (h)Impact of labor (%)
RE0379

Sealing widespread cracks and cracks in the brick factory

1,0015,6015,607,930,6050,83
Sealing of widespread cracks and cracks in the brick factory, with lime bastard mortar and dosing cement m-160b (1: 0.25: 3) natural color, even finishing, color and texture samples to choose existing Pressure air, then the prepared mortar will inject it with a pistol filling, removing mortar discomfort and cleaning the surface as the seal is performed.
%01%Auxiliary costs0,020,30
%02%Indirect costs0,030,45
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0208kgPB-II asphalt rubber rubber sticker0,024,460,09
REU0209uElastomeric0,0340,001,20
REU0203hResin injection equipment0,101,220,120,120,10
REU0206kgEpoxy resin for injections0,3416,205,48
REU0207uInjection nozzle resins1,500,100,15
MOU0005h1st officer under construction. Professional level VIII (Source: IVE). / More information0,1817,933,233,230,18
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information0,3214,314,584,580,32
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 04/11/2014
Zone València
Remarks: AV0001
..........
Validated by ?
Profile ?
Validated by date 00/00/0000
Remarks: Notes del validador?
edit price