RE0389u

Healthy anchors railing and repair factory work. Railings of balconies. Main facade.

1,0043,4143,4120,662,1747,59
Healthy and repair of the rail anchors embedded in the brick sill, balconies on each level of the main facade through the surface cleaned and chopped loose or damaged, cracked or lifted the deterioration of the section anchored, removal of these coatings with manual or mechanical means to reach at least the embedded steel railing and oxidation causes pumping. It will carry out a cleaning of said steel rust and strengthen, if necessary, injection resins, embedded in his leg. Cleaning brush with anchoring spikes, with subsequent application of mortar adhesion prior protection of steel with a passivating brand SIKA Monotop 910 or similar, in two layers, regeneration volume to reconstruct the original form sill work with a mortar based on cement and synthetic resins, silica fume and polypropylene fibers brand SIKA 612 Monotop similar or even auxiliary pp, removal of excess material, loading debris; fully prepared for later painted only in this area, not included in this game.
%01a%Ancillary costs of labor0,020,41
%02%indirect costs0,031,25
%Según Increase the difficulty of grado or Incertidumbre1,00
REU0264uHilti electric demolition hammer / Kango.0,1516,002,40
REU0145kgSika Armatec top 110 Period-corrosion inhibitor and bonding can 4kg, three components: A + B + C.0,214,150,87
REU0031kgMortar structural resins, Aplicatec R4 product in bags of 25 kg.8,500,655,53
REU0203hResin injection equipment0,681,220,830,830,68
REU0204hmechanical drill0,282,350,670,670,29
REU0206kgEpoxy resin for injections0,5516,208,91
REU0015kgSteel profiles B-500 S-6 / 16mm rods corrugated cut supplies on site.1,000,780,78
REU0104Mortar cement CEM II / B 32.5 N P-type M-5, made on site with 250 kg / m³ and a cement volume ratio 1/6.0,02115,502,31
REU0036m44 Armatex fiber mesh plaster.0,350,820,29
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information0,5517,939,869,860,55
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information0,6514,319,309,300,65
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 15/11/2014
zone València
observations: AO0005
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?
Edit price