Code | One | Description | Amount | Price (€) | Amount (€) | Impact of labor (€) | Labor (h) | Impact of labor (%) |
RE0389 | u | Sanoado and repair the railing anchors at the work factory. Preparations of the balcony. Main facade. | 1,00 | 43,41 | 43,41 | 20,66 | 2,17 | 47,59 |
| | Sanoado and repair of the anchors of the railing embedded in the brick factory that was struck, at each level of balconies to the main facade, by chopped and sanitized of the loose or poor condition, cracked or raised by the deterioration of the anchored section, Elimination of the. These coatings with mechanics or manuals mean until at least the steel embedded in the railing and the oxidation of which causes the approach. The cleaning of oxides of this steel will be made and strengthened, if necessary, with resin injection, in its built section. BARBECOA ANCORAGE CLEANING A mortar based on cement and synthetic resins, silica smoke and polypropylene fibers of the Sika Monotop 612 or similar mark, even P.P. Auxiliary means, elimination of excess material, load of waste; Fully prepared for subsequent painting only in the area, not included in this article. | | | | | | |
%01a | % | Auxiliary costs on the labor | 0,02 | | 0,41 | | | |
%02 | % | Indirect costs | 0,03 | | 1,25 | | | |
| % | AUMENT DE ACUERDO WITH THE GRADO OF DIFFICULTY OR Uncertainty | 1,00 | | | | | |
REU0264 | u | Hilti / Kango Electric Hammer electric. | 0,15 | 16,00 | 2,40 | | | |
REU0145 | kg | SIKA CORROSION INHIBITOR AMBATEC Top 110-Epocem and Union Bridge, 4kg Boat, 3 components: A+B+C. | 0,21 | 4,15 | 0,87 | | | |
REU0031 | kg | Mortar of structural resins, R4 applied product, in bags of 25 kg. | 8,50 | 0,65 | 5,53 | | | |
REU0203 | h | Resin injection equipment | 0,68 | 1,22 | 0,83 | 0,83 | 0,68 | |
REU0204 | h | Mechanical drill | 0,28 | 2,35 | 0,67 | 0,67 | 0,29 | |
REU0206 | kg | Epoxy resin for injections | 0,55 | 16,20 | 8,91 | | | |
REU0015 | kg | B-500-S 6/16mm Profiles of corrugated, cutting and supply steel. | 1,00 | 0,78 | 0,78 | | | |
REU0104 | m³ | CEM II/B-P 32.5 N Type M-5 Mortar of cement, work with 250 kg/m³ of cement and a proportion to volume 1/6. | 0,02 | 115,50 | 2,31 | | | |
REU0036 | m | Armatex mesh fiber 44 plaster. | 0,35 | 0,82 | 0,29 | | | |
MOU0005 | h | 1st officer under construction. Professional level VIII (Source: IVE). / More information | 0,55 | 17,93 | 9,86 | 9,86 | 0,55 | |
MOU0006 | h | Ordinary pawn under construction. Professional level XII (Source: IVE). / More information | 0,65 | 14,31 | 9,30 | 9,30 | 0,65 | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Written by Vicente Almudéver | | | | | | |
| | | | | | | | |
| | Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Update 15/11/2014 | | | | | | |
| | Zone València | | | | | | |
| | Remarks: AO0005 | | | | | | |
| | .......... | | | | | | |
| | Validated by ? | | | | | | |
| | Profile ? | | | | | | |
| | Validated by date 00/00/0000 | | | | | | |
| | Remarks: Notes del validador? | | | | | | |
| | edit price | | | | | | |
|