Code | One | Description | Amount | Price (€) | Amount (€) | Impact of labor (€) | Labor (h) | Impact of labor (%) |
RE0478 | m | Chopped and removal of ceramic revolt, for reinforcement of MVV Mecanoviga | 1,00 | 9,48 | 9,48 | 6,68 | 0,45 | 70,46 |
| | Chopped plaster on the horizontal walls of the base shoe base that will be strengthened or disinfected until they are completely seen and cleaned the lower face of them for the correct union between them and the reinforcement system used, even the part Produced proportional of the demolition of the intertwined rivers of the slab's bovas for the correct execution of the reinforcement actions of the beams depending on the system used, cleaning, collected and loading waste at the loading foot. | | | | | | |
%01a | % | Auxiliary costs on the labor | 0,02 | | 0,13 | | | |
%02 | % | Indirect costs | 0,03 | | 0,27 | | | |
| % | Estimation of the degree of difficulty or uncertainty (normal: 1.00) | 1,00 | | | | | |
REU0264 | u | Hilti / Kango Electric Hammer electric. | 0,15 | 16,00 | 2,40 | | | |
MOU0023 | h | Specialist pawn under construction. Professional level XI (Source: IVE). / More information | 0,20 | 15,50 | 3,10 | 3,10 | 0,20 | |
MOU0006 | h | Ordinary pawn under construction. Professional level XII (Source: IVE). / More information | 0,25 | 14,31 | 3,58 | 3,58 | 0,25 | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Written by Vicente Almudéver | | | | | | |
| | | | | | | | |
| | Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | Update 01/07/2015 | | | | | | |
| | Zone València | | | | | | |
| | Remarks: AO0012 | | | | | | |
| | .......... | | | | | | |
| | Validated by ? | | | | | | |
| | Profile ? | | | | | | |
| | Validated by date 00/00/0000 | | | | | | |
| | Remarks: Notes del validador? | | | | | | |
| | edit price | | | | | | |
|