REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0490u

Demolition of balconies Trays

1,00110,50110,5076,995,0069,67
Total demolition of bin concrete balcony spoiled by mechanical, considering that previously ensure the stability of the existing railing cast on her plate atirantándola by struts of 50.3 mm and length sufficient taken from each of the two corners, tilted 45 degrees to find the front wall and built-in 10cm claw ready to effect this plate, falcada mortar anchor. It will begin demolishing the balcony for more bottom end and more superior, thus facilitating the necessary propping and formwork. Demolition run up to the mark in front of the wall. Even collection, downloading and transport of debris to landfill.
%01a%Ancillary costs of labor0,021,54
%02%indirect costs0,033,17
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
REU0264uHilti electric demolition hammer / Kango.1,8016,0028,80
MOU0005hOfficial 1st in construction. Professional level VIII (Source: IVE). / More information1,5017,9326,9026,901,50
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information3,5014,3150,0950,093,50
observations:
Not Rated remove the existing metal railing balconies or healthy work, strengthening encastaments, reconstruction of elements and / or replacement thereof.
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 01/07/2015
zone València
observations: AO0012
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?
Edit price