REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CodeOneDescriptionAmountPrice (€)Amount (€)Impact of labor (€)Labor (h)Impact of labor (%)
RE0490u

Demolition of balcony trays

1,00110,50110,5076,995,0069,67
Total demolition of the concrete balcony in poor condition due to the two corners, inclined to 45º until you find the facade and built on the wall of 10 cm. The demolition of the lower balcony will begin and end the highest, thus facilitating the attached files and the necessary formwork. The demolition will run even on the wall of the facade. Even the collection, fall and transport of the controlled landfill.
%01a%Auxiliary costs on the labor0,021,54
%02%Indirect costs0,033,17
%Estimation of the degree of difficulty or uncertainty (normal: 1.00)1,00
REU0264uHilti / Kango Electric Hammer electric.1,8016,0028,80
MOU0005h1st officer under construction. Professional level VIII (Source: IVE). / More information1,5017,9326,9026,901,50
MOU0006hOrdinary pawn under construction. Professional level XII (Source: IVE). / More information3,5014,3150,0950,093,50
Remarks:
It is not valued to eliminate the existing metal railing on the balconies, or the sanitized works, the recessed reconstruction, the reconstruction of elements and/or the replacement of them.
Company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
Update 01/07/2015
Zone València
Remarks: AO0012
..........
Validated by ?
Profile ?
Validated by date 00/00/0000
Remarks: Notes del validador?
edit price