CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0504u

Demolition of existing masonry chamber

1,0034,5234,5232,872,7595,22
Demolition and construction raised chests existing walk down or step inside a local or patios, medium-sized 50x50x60 cm, to launch new route sanitation, even hearth base and excavation of land surplus through hydraulic hammer compressor, removal of debris and cargo portable container located on public roads.
%01a%Ancillary costs of labor0,020,66
%02%indirect costs0,030,99
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0006hOrdinary laborer in construction. Professional XII (Source: IVE). / More information1,0014,3114,3114,311,00
MOU0023hPawn specialist in construction. Professional XI (Source: IVE). / More information1,0015,5015,5015,501,00
REU0184hJackhammer devastating0,754,083,063,060,75
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 01/07/2015
zone València
observations: AO0015
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?
Edit price