Steel structures

CODEUDESCRIPTIONPRICE
RE0017

Finishing synthetic enamel on wood with steel handrails on both sides.

Synthetic enamel, black, glossy finish on surface of iron or steel, cleaning and surface preparation to paint, using manual methods to leave it free of grease, finishing with both hands with synthetic enamel with a minimum thickness of the 35 micron dry film ma (yield: 0.08 l / m²)

16,55 €
RE0133u

Placing anchor plate steel S-275-JR, 250x250x10 mm.

Supply and installation of anchor plate steel S-275-JR and dimensions 250x250x10 mm, with 4 holes 14 mm, arranged on concrete edge beam, drills and chemical anchor with epoxy resin or similar type DESA-CHEM, 12 mm galvanized threaded rod, nut and flat washer on basic regularized with mortar type resins AplicatecR4 or similar corrosion protection paint Thkrom or similar union and L100x100x10 mm welded angle as an element of the support beam; unit fully placed, proportional means and scaffolding necessary aid, removal of excess material and final cleaning.

42,63 €
RE0081m

Empresillt PNL-pillar 40x40 cm 100.10 mm

Strengthening support rectangular concrete dimensions of 40x40 cm confinement lattice of four standardized profiles hot rolled steel PNL-S275 100.10 mm 15 kg / m according to UNE 10025-2 willing to support the edges and joined in platabandes all four sides by metal welded joint in situ, each 25 cm by constriction cooling even contribution of welding material according to UNE-EN ISO 2560, worked and placed.

254,83 €
RE0164u

Waste Management Study for rehabilitation cranes (10 IU)

Writing Study Waste Management for the works described in the implementation plan of rehabilitation intervention cranes 10 inspection units, according to the provisions of Royal Decree 105/2008, February 1, 2008, the Ministry of the Presidency, which regulates the production and management of construction and demolition waste.

263,67 €
RE0079

Microfiber mesh protection vertical work

Supply, installation and dismantling mesh protection in vertical work, consisting of dense microfiber mesh density even fasteners and anchors fixed points. Not including daily rental.

3,23 €
RE0107u

Assembling and dismantling shelter for pedestrians. Section 15 ml.

Erection and dismantling of structures of protection for pedestrians, with free passage 1.5 meters wide and 3.0 meters high, consisting of tubular hot galvanized steel with higher ceiling protection of pedestrians and peaked at 45 ° angle to avoid falling objects, ready for installation after a scaffolding at heights as a basis for the execution of facade of 15 m, according assembly drawings. Even accessories, security systems, anchors and replacements.

550,17 €
RE0398u

Protection of interior furnishings

Protection of furniture inside a house or premises prior to intervention work by its cover with transparent polyethylene sheet and dismounted elements susceptible to breakage as mirrors, etc.

85,77 €
RE0487u

Privacy passive RF-90 Rock wool.

Passive fire protection of all metallic elements arranged in the project. Both reinforcements existing profiles IPE beams under as UPN conforming the beam as well as new profiles reinforcement system Mecanoviga worth measuring. Made by projecting mortar fire retardant rock wool for metal structures for achieving RF-90.

23,11 €
RE0222u

Prosthesis wooden frames fiberglass.

Repair deteriorated area eliminating the beam and placing a prosthetic meteixa section of the existing beam up to 30 cm of sawn pine (Pinus sylvestris), brushed finish for structural applications, structural quality MEG as UNE 56544, resistant class C-18 according to UNE-EN 338 and UNE-EN 1912 and protect against biotic agents that corresponds to the kind of penetration NP2 (3 mm on the sides of the sapwood) according to UNE-EN 351 -1, attached to healthy wood with epoxy-acrylate, styrene-free, and then arming the union of two wood sticks with two fiberglass reinforced polyester resin, 12 mm in diameter, 0 , 05 meters long each, housed in holes made in the prosthesis and healthy wood. Even proportion of healthy piece of wood, cut at 60 ° to healthy wood to receive the prosthesis, fixing provisional prosthesis jacks and wooden nails, execution of drilling in the prosthesis and wood healthy epoxy resin poured into the perforations after placing the rods, polished imperfections, cleaning, collection, removal and manual loading rubbish truck or container.

102,07 €
RE0173u

Drafting building rehabilitation project (1 UI)

Writing rehabilitation project execution for the first inspection unit, consisting of drafting and assessment of the supplementary report from the building, study and assessment of the coves executed (if any) and description of the solution repair of pathologies detected in structure, roofing, façades and facilities. Includes tours and travel, visit expert for inspection of the property, the report document specification, budget and plans.

2.927,74 €
RE0171u

Drafting building rehabilitation project (10 IU)

Writing implementation plan for building restoration or local inspection with 10 units, consisting of drafting and assessment of the supplementary report from the building, study and assessment of the coves executed (if any) and description of the solution for the repair of pathologies detected in structure, roofing, façades and facilities. Includes tours and travel, visit expert for inspection of the property, the report document specification, budget and plans (with an intensity of inspection least 10 IU).

5.047,17 €
RE0172u

Drafting building rehabilitation project (20 IU)

Writing implementation plan for a building renovation or 20 local inspection units, consisting of drafting and assessment of the supplementary report from the building, study and assessment of the coves executed (if any) and description of the solution for the repair of pathologies detected in structure, roofing, façades and facilities. Includes tours and travel, visit expert for inspection of the property, the report document specification, budget and plans (with an intensity of inspection least 20 IU).

6.156,96 €
RE0168u

Drafting building rehabilitation project (50 IU)

Writing implementation plan for a building renovation or 50 local inspection units, consisting of drafting and assessment of the supplementary report from the building, study and assessment of the coves executed (if any) and description of the solution for the repair of pathologies detected in structure, roofing, façades and facilities. Includes tours and travel, visit expert for inspection of the property, the report document specification, budget and plans (with an intensity of inspection least 30 IU).

8.201,33 €
RE0215u

Strengthening collar based on concrete pillar 25x25 cm, with PNL40.4

Base reinforced concrete pillar dimensions 25x25 or diameter 25 cm with metal collars of PNL-angle 40.4 mm hot rolled S275 steel, joined together by welding, including welding and in situ filling of space between concrete and steel with a layer of 1.5 mm epoxy two components.

124,55 €
RE0008m

Reinforcing wrought IPE-100 to 3.50 m. Includes preliminary work and shoring.

Functional replacement of slabs, in areas identified in plans, each consisting of reinforcing beam profiles using IPE-100 S-275-JR, according to the description of the Project and the Project Management indications, including the following materials and works:

94,35 €
RE0009m

Reinforcing wrought IPE-120 to 3.5 m. Includes preliminary work and shoring.

Functional replacement of slabs, in areas identified in plans, each consisting of reinforcing beam profiles using IPE-120 S-275-JR, according to the description of the Project and the Project Management indicacionsde, including the following materials and work:

99,64 €
RE0010m

Reinforcing wrought IPE-140 up to 4 m. Includes preliminary work and shoring.

Functional replacement of slabs, each consisting of reinforcing beam profiles using IPE-140 S-275-JR, including the following materials and works:

105,16 €
RE0011m

Reinforcing wrought IPE-160 to 3.5 m. Includes preliminary work and shoring.

Functional replacement of slabs, in areas identified in plans, each consisting of reinforcing beam profiles using IPE-160 S-275-JR, according to the description of the Project and the Project Management indicacionsde, including the following materials and work:

112,60 €
RE0216m

Metal reinforcement concrete pillar 25x25 cm, with PNL40.4

Strengthening support rectangular concrete dimensions of 25x25 cm confinamiemto lattice of four standardized profiles hot rolled steel S275 PNL-40.4 mm 2.42 kg / m according to UNE 10025-2 willing to support the edges and joined in platabandes all four sides by metal welded joint in situ, each 25 cm by constriction cooling even contribution of welding material according to UNE-EN ISO 2560, worked and placed.

310,31 €
RE0250u

Repair Cabot beam wooden frames with carbon fiber.

Repair any wooden beam, cutting the area damaged or degraded by the solid-dumping gravity of 30 kg mortar fluid two-component epoxy resin base, upon placement of the armor 4 bars carbon fiber embedded in an epoxy matrix, MB Construction Chemical- -BASF 165/2500 of 8 mm diameter and 800 mm in length each, anchored in the beam with epoxy resin, styrene-free, high-resistance, applied filter dosing and mixing machine in holes made in the healthy part of the wood. Even w / w mounting system formwork in the area to intervene, placing protective film of polyethylene, sealing the formwork to prevent leaks, cleaning and priming of wood with epoxy grout mortar of the same, the dismantling formwork system, gathering, removal and manual loading debris truck or container.

472,31 €
RE0310m

Structural repair of concrete in front of forged 35 cm.

Repairing front forged in balconies and terraces with removal of the entire coating was deficient by mechanical or manual to get at least reinforced steel oxidation causes the peeling. It will clean out this armor oxide in its entirety and contour by sandblasting or brush fence, for subsequent passivation using an appropriate pasivante types SIKA TOP 108 or similar, in two layers and regeneration , to reconstruct the original form of the piece to repair with a mortar or similar type Monotop 650 prior surface treatment of existing concrete type latex emulsion adhesion. If you need to have reached an excessive degree of oxidation, will be replacing the frames needed for other similar features at least, even loading and transport of debris to landfill authorized.

36,00 €
RE0116m

Repair or replacement parts ceramic socket.

Repair or replacement of ceramic piece socket type messed finished in perimeter roof, perforated piece of mortar binding, layout similar piece taken with cement mortar 1: 6, final cleaning and grouting works.

8,31 €
RE0064m

Repair occasional song wrought lining, width 35 cm.

Healthy singing and repair 35 cm wide wrought seen in forward and rear main access to housing, chopped previous coating cracked or damaged, healthy structural concrete structural passive armor and reconstruction of the affected section mortar AplicatecR4 resin type or similar reconstruction of edges and surface finish plastering cement mortar 1: 6 good view, final application of coating silicate paint in shades similar to the existing one, including auxiliary, scaffolding needed , removal of excess material and cleaning.

39,53 €
RE0218

Cleaned floors of small beams and structural repair.

Intervention in concrete beam consisting of: chopped roof lining wetlands to achieve joists, healthy cepilladora armor with manual handling of frames affected by oxidation product using passive beam reconstruction using special mortars or sika similar

34,11 €
RE0135u

Supply and installation anchor plate HERMS

Supply and installation of anchor plate HERMS with four anchors 12 mm, arranged on concrete edge beam, drills and chemical anchor with epoxy resin or similar type DESA-CHEM, 12 mm galvanized threaded rod, nut and washer Flat on base regularized with mortar type resins AplicatecR4 or similar corrosion protection paint Thkrom or similar; unit fully placed, proportional means and scaffolding necessary aid, removal of excess material and final cleaning.

44,58 €